What a lender looks for in your feasibility

The feasibility is the first document a credit assessor reads and the one they return to most. A strong project with a weak feasibility gets priced as a weak project.

Before a lender looks at the site, the builder or the borrower, they read the numbers. Here is what a credit assessor will test in your feasibility, and where applications most often come unstuck.

1. Realisation values backed by evidence

The lender will commission its own independent valuation. The gross realisation value in your feasibility should sit at or below what a valuer can support with comparable sales. Pricing ahead of the evidence is the first thing to be cut, and when it is, every ratio in the application moves with it.

2. A complete cost base

Assessors look for costs that are missing as much as costs that are high. A complete feasibility includes:

  • Land and acquisition costs, including stamp duty.
  • Construction costs supported by a fixed-price building contract or a quantity surveyor's cost report.
  • Professional fees: architect, engineers, consultants and project management.
  • Council and authority contributions, permits and headworks.
  • Marketing, sales commissions and legal costs.
  • GST, treated correctly for the project, including whether the margin scheme applies.
  • Finance costs: establishment and line fees, and interest capitalised over the full program.
  • A construction contingency, commonly around 5% and higher for complex builds.

3. A margin that survives scrutiny

Lenders test the profit margin on cost after every expense, including finance. Many look for a meaningful buffer, often in the range of 15% to 20% or more depending on the lender and the project. If the margin only works at best-case pricing, the assessor will see it.

4. Presales that qualify

Not every contract counts. Lenders generally want arm's-length buyers, unconditional contracts, proper deposits and sunset dates that fit the build program. Some lenders discount related-party sales or certain foreign purchasers, and bank lenders often require presales to cover a set share of the debt.

5. The builder and the program

The lender will assess the builder's experience on similar projects, its financial capacity and the terms of the building contract. The program needs to be realistic: the lender's quantity surveyor will review it and monitor progress against it at every draw.

6. Equity and the people behind it

Expect questions about how much equity you are contributing, where it comes from and when it goes in. It is usually required up front, before the first drawdown. Your track record, the borrowing entity and the guarantors are assessed alongside the numbers.

7. A sensitivity analysis

Show what happens if sale prices fall 10%, costs rise 10% or the program runs six months late. A feasibility that includes its own stress test tells the assessor you have already asked the hard questions.

8. A clear exit

Finally, the lender needs to know how it gets repaid: settlement of presales, sale of the remaining stock, or a refinance to a residual stock or investment facility. The exit should be credible on the day the build finishes, not just on the day you apply.

Where feasibilities most often fail

  • Interest left out or understated, particularly over an extended program.
  • GST ignored or counted twice.
  • Construction costs that do not match the builder's contract.
  • A sources and uses table that does not reconcile to the total cost.

We review and rebuild feasibilities to lender standard before they are submitted, so the assessor's questions are answered in the first read.

This article is general information only and is not credit, financial, tax or legal advice. It does not take into account your objectives, financial situation or needs. Lending criteria, fees and terms vary between lenders and change over time. Speak with us about your circumstances before making a decision.